HS2 / Accountability tracker
Curated figures · verified 31 October 2026
Dataset 2026-10-31a

Two thirds of the money spent. One third of the work done.

Every figure below is taken from a published source and carries the reference. Cost figures are only comparable within a single price base, so the basis is a control, not a footnote.

Programme position

Price base

Spend to September 2025 in nominal prices, future work in 2025 prices. The 2020 estimate was never published on this basis, so it cannot be set against the current range.

£0bn£20bn£40bn£60bn£80bn£100bn
Estimate to completeDfT, May 2026
£87.7bn – £102.7bn
HS2 Ltd ambitionMark Wild, May 2026
£93.2bn
Paid to Jul 2026HS2 Ltd payments, DfT data
£49.3bn
2020 estimate, Phase 1not comparable
Not published on this basis
Paid to July 2026 £49.3bn

HS2 Ltd payments of £25k or more since January 2017, nominal prices, from DfT monthly spending data. Includes payments for the cancelled Phase 2.

DfT spending over £25k · 2026-10-29

Totalled from 115 DfT monthly files, January 2017 to July 2026, excluding a £590m VAT remittance to HMRC in July 2019. The NAO put total programme expenditure at £46.8bn to 31 March 2026 (HC 52), on a different basis. https://www.gov.uk/government/collections/dft-departmental-spending-over-25000

Cost of the reset itself £153m

Expected total. £101m spent by 31 March 2026. The reset runs from January 2025 to spring 2027.

NAO HC 52 · 2026-06-29

Nominal prices. The reset concludes with a fully assured cost and schedule baseline in spring 2027. https://www.nao.org.uk/reports/high-speed-two-reset/

Consultancy, 2025–26 £77.8m

HS2 Ltd spend on consultancy in the financial year, stated in answer to a Lords oral question.

Hansard, Lords · 2026-06-22

Lord Hendy of Richmond Hill, HS2 Ltd: Consultants, House of Lords, 22 June 2026. https://hansard.parliament.uk/Lords/2026-06-22/debates/005F6C33-3A0E-40B8-A77B-805C7043D65D/HS2LtdConsultants

Costs found disallowable ~£500m

Identified by HS2 Ltd and the main works civils and stations contractors as outside contract scope or unsupported by records, as at May 2026.

NAO HC 52 · 2026-06-29

Cost verification now runs quarterly. Where costs are disallowed, HS2 Ltd adjusts expenditure and seeks recovery from the joint ventures. https://www.nao.org.uk/reports/high-speed-two-reset/

Cost and schedule

When it opens, and what it costs to get there

The May 2026 estimate is a range, not a number. HS2 Ltd's chief executive has set an ambition inside the lower half of that range; the NAO view is that the estimate still carries high uncertainty until the baseline lands in spring 2027.

20302032203420362038204020422044
Earliest opening2020 schedule
2031
Opening stageOld Oak Common – Curzon St
May 2036 – Oct 2039
HS2 Ltd ambitionfirst passenger services
late 2037
Full schemeincl. Euston and Handsacre
May 2040 – Dec 2043

Station estimates since 2020

Old Oak Common — Programme cost estimate×2.2 since 2020
2020£2.0bn
2026£4.3bn
Birmingham Curzon Street — Programme cost estimate×2.2 since 2020
2020£0.6bn
2026£1.3bn
What drove the increase ⅔ / ⅓

Two thirds from scope missed at the outset, underestimation and inefficient delivery. One third from inflation.

DfT report to Parliament · 2026-05-19

Cost estimates will now be refreshed for inflation every two years rather than held for seven. https://www.gov.uk/government/speeches/hs2-6-monthly-report-to-parliament-may-2026

Delay against the 2020 schedule ~13 years

Latest date the full railway could open is December 2043, against an earliest 2031 on the 2020 schedule.

NAO HC 52 · 2026-06-29

Civil engineering across the line of route is at least four years behind; testing and commissioning was underestimated by roughly a further three. https://www.nao.org.uk/reports/high-speed-two-reset/

Euston EDC from Apr 2026

Now an executive non-departmental public body sponsored by DfT. Chief executive and chair still being appointed. A PPP for the HS2 station is being explored.

GOV.UK · 2026-10

Took the directing role for the Euston campus in April 2026. DfT told the PAC on 14 September 2026 that chief executive interviews had been held. Early market engagement began October 2025; the first stage of preliminary market engagement followed in February 2026, testing appetite for a design, build, finance and maintain structure. Trade press reported at the end of October 2026 that the chief executive search was still running and the search for a chair had been paused. https://www.gov.uk/government/organisations/euston-delivery-company

Spent on works at Euston £3.8bn

Spent by March 2026, before any HS2 station there is contracted.

PAC session notice · 2026-09-14

Stated in the Public Accounts Committee notice for its 14 September 2026 session, drawing on the NAO report. https://committees.parliament.uk/event/28101/formal-meeting-oral-evidence-session/

The transparency gap

What has been paid, against what was published

Contracts commit money before it is spent, so the declared value of award notices should sit above cumulative payments. Until 2019 it did. Payments overtook declared value in 2020, and the distance has widened every year since.

£25.4bn Cumulative gap at 2025 £45.1bn paid to suppliers since January 2017 against £19.7bn of declared contract value — published notices account for 44% of what has gone out of the door. Payments have since reached £49.3bn by July 2026, a further £4.14bn in 2026; the notice series is not yet compiled for 2026.
Cumulative HS2 Ltd payments since January 2017, DfT data £25k and over Cumulative declared value of award notices
£0£10.4bn£20.9bn£31.3bn£41.8bn£52.2bn20182019202020212022202320242025Jul 2026£49.3bn to Jul 2026notices: 2026 not yet compiledpayments overtake declared value
Sep 2023£14.7bn£24.7bn spend against £9bn of contracts published — written evidence to PAC
Jul 2025£21.8bnPosition set out in correspondence with the HS2 Ltd chief executive
2025£24.3bnComparison published January 2026, on the earlier payment series
Oct 2026£25.4bnEnd-2025 position with payments rebuilt from every DfT monthly file since January 2017

A worked example: Fujitsu

Published on Contracts Finder£7.6macross 6 award notices
Actually paid, DfT data£32.0mat least, to end July 2025 — 4.2× the published figure

Notices by platform, published since 1 January 2021

Notice typeContracts FinderFind a TenderFTS as share of CF
Contract (tender) notices2063316%
Contract award notices, value over £115,6582473715%

Publication on Find a Tender is a treaty obligation under the WTO Government Procurement Agreement and the UK–EU Trade and Cooperation Agreement. The difference in notice format between the two platforms does not account for a gap of this size.

PAC written evidence · 2023-11

Written evidence to the Committee of Public Accounts, HS2 and Euston: Recall (HS20003). committees.parliament.uk/writtenevidence/126367/pdf/

Asking for the figures behind the gap — FOI-26-6379

HS2 Ltd wrote on 6 March 2026 (CEO-25-1496) that the gap between published award values and published spend is not disputed, and that the four Main Works Civils Contracts costing more than their estimates at award "will form a major part of the gap". The request asked for the figures behind that explanation.

7 of 8 items withheld. Received 23 September 2026; answered October 2026, late. Handled under the Environmental Information Regulations 2004, not FOIA. Public interest held to favour withholding "at this time" because the contracts are being renegotiated, and to protect confidential Board reporting. The EKFB and Align deeds of variation had been signed on 31 July 2026, before the request was made.

#Asked forOutcomeException
1Total of the Prices for each contract at the start of Stage 2, April 2020 WithheldEIR 12(5)(d), 12(5)(e)
2Total of the Prices now, with all implemented compensation events WithheldEIR 12(5)(d), 12(5)(e)
3Value of compensation events implemented since Notice to Proceed WithheldEIR 12(5)(d), 12(5)(e)
4Latest Anticipated Final Cost reported to the Board or ARAC WithheldEIR 12(5)(d), 12(5)(e)
5Cumulative Price for Work Done to Date certified WithheldEIR 12(5)(d), 12(5)(e)
6Value of the new EKFB and Align agreements, and of each contract just before signature WithheldEIR 12(5)(d), 12(5)(e)
7Latest consolidated schedule of contract values given to the BoardNo consolidated schedule; values were reported to the Board by project, last in June 2024. WithheldEIR 12(5)(d), 12(5)(e)
8Whether an award, UCR reg 88(5) modification or PA23 change notice was published for the EKFB and Align agreements, and the ground relied onThe agreements were deeds of variation to UCR 2016 contracts, considered under reg 88, so no PA23 notice and no award notice was required. The response does not say whether a reg 88(5) modification notice was published, or which permitted ground was relied on. Partly answered
EIR response FOI-26-6379 · 2026-10

Response, Annex A (item-by-item answers) and Annex B (public interest tests). whatdotheyknow.com. Premise from HS2 Ltd letter CEO-25-1496, 6 March 2026.

How a contract goes missing from the record

Published on Find a Tender but not on Contracts Finder

£1.97bn

HS2 Rolling Stock Manufacture and Maintenance Services — Hitachi Rail Limited

FTS notice 2022/S 000-000805, published 11 January 2022. Value excluding VAT £1,970,000,000.

Award notice published with a value of zero

£0

Resilience and Assurance Framework Agreement for Interchange Station — Skanska Construction UK Limited

Published 28 September 2022 on Contracts Finder with a total contract value of £0.

Award notice published without naming the supplier

£130,625

BBV HS2 MWCC North, Delta Junction — PSV erection tools certification technical assistance

Published 30 November 2022. Supplier recorded as the notice publisher rather than the contractor.

No updated notice when the contract value rises

Not declared

Main works civils, Stage 1 award

OJEU TED notice 344354-2017 declared the value as "Variable". No Stage 2 construction award notice appears on any platform.

Contract reset by deed of variation, with no notice and the value withheld

Withheld

Main works civils, EKFB and Align, deeds of variation signed 31 July 2026

HS2 Ltd says no award notice or Procurement Act change notice was required, as these were modifications to UCR 2016 contracts. Old and new values were withheld under EIR 12(5)(d) and 12(5)(e) in response to FOI-26-6379.

Read the two series with care — they are not like-for-like

  • Total payments include spending never procured through a published contract at all — land and property, staff and running costs, and third-party agreements.
  • Some contract spend requires no notice: framework call-offs, orders below threshold, and variations agreed within an existing contract.
  • HS2 Ltd procured under the Utilities Contracts Regulations 2016, under which much Contracts Finder publication was voluntary rather than mandatory.
  • The payment series counts HS2 Ltd payments of £25k or more in DfT monthly transparency data from January 2017. Files to May 2018 listed payments over £500; only rows of £25k or more are counted. A £590m VAT remittance to HMRC in July 2019 is excluded. September 2018 looks incomplete in the published file (£27.9m, against about £150m in neighbouring months).
  • The NAO figure of £46.8bn to March 2026 is total programme expenditure on a different basis from the £49.3bn of payments to July 2026, and the two should not be netted against each other or compared as like for like.
Compiled analysis · 2026-01

Notice series compiled by Chris Smith MCIPS from Contracts Finder, Find a Tender and OJEU TED, January 2026. Payment series rebuilt October 2026 from all 115 DfT monthly spending files, January 2017 to July 2026 (HS2 Ltd entity rows). Blue marker: independent compilation rather than a departmental publication. HS2 Ltd does not dispute that the gap exists; what it signifies is contested.

Contracts and suppliers

The commercial reset, package by package

The 2020 commercial model put nearly all risk on the taxpayer and did not reward hitting cost or schedule targets. The £15bn allocated in 2020 for the Phase 1 main civils was exhausted by 2024 with the works far from finished. Renegotiation has run on a verified-cost basis since April 2025 and is not yet complete.

PackageHeld byScopeValueReset status
Main works civils — north Chilterns to Warwickshire EKFBEiffage, Kier, Ferrovial Construction, BAM Nuttall 80km Withheld Deed of variation signed 31 Jul 2026
Main works civils — outer London and south Bucks AlignBouygues Travaux Publics, Sir Robert McAlpine, VolkerFitzpatrick 24km incl. Chiltern Tunnel, Colne Valley Viaduct Withheld Deed of variation signed 31 Jul 2026
Main works civils — West Midlands Balfour Beatty VINCI 90km Withheld In negotiation · target: Christmas 2026
London tunnels Skanska Costain STRABAG 21km, West Ruislip to Euston Withheld In negotiation · target: Christmas 2026
Old Oak Common station Balfour Beatty VINCI SYSTRA 14-platform interchange ~£1bn Award value, pre-reset
Birmingham Curzon Street station Mace Dragados 7-platform terminus ~£570m Award value, pre-reset
Interchange station, Solihull Laing O'Rourke 4-platform station ~£370m Award value, pre-reset
Euston HS2 station Euston Delivery Company (client) Design stage; PPP under exploration — Not contracted
Rolling stock and 12-year maintenance Hitachi-Alstom High Speed (HAH-S) 54 trains — Newton Aycliffe, Derby, Crewe £1.97bn Award value, Dec 2021
Washwood Heath rolling stock depot and Network Integrated Control Centre TWA JVTaylor Woodrow Infrastructure, Aureos Rail 70ha site, Birmingham ~£856m Awarded May 2026, during the reset

Station and rolling stock values are as awarded and pre-date the reset; they are not restated on the May 2026 basis. HS2 Ltd told the PAC in September 2026 it expects to realign two station contracts and the rolling stock contract to the reset programme by March 2027. The Washwood Heath depot value is as reported at award. Station programme cost estimates — which cover far more than the construction contract — are shown separately above.

Every published award

All HS2 Ltd contracts, as published

Every contract award, modification and voluntary transparency notice published with HS2 Ltd as the buyer — on Contracts Finder since 2015, Find a Tender since 2021, and the EU's TED. One row per awarded lot. The same award published on more than one platform is counted once. Values are as declared in the notice: a contract's value when awarded, not what has been paid.

958contracts, 2015–2026
£17.9bndeclared, excluding frameworks
£1.34bnframework ceilings
39published with no value
3published with no supplier
PublishedContractSupplierDeclared valueNotice
Loading…
Compiled analysis · 2026-10-30

Contracts Finder searched month by month for “HS2”, “High Speed Two” and “High Speed 2”, kept where the publishing organisation is HS2 Ltd. Find a Tender: every release since January 2021 (326,595), kept where HS2 Ltd is a buyer by Companies House number or name. TED: notices with HS2 Ltd as buyer, with suppliers and lot values read from the notice XML. Notices published by HS2's own contractors (EKFB, BBV, SCS, Align and others) are not HS2 Ltd contracts and are excluded. Duplicates are matched automatically by supplier and value, by identical value over £1m within 400 days, or by a Contracts Finder value equal to a whole multi-lot notice. TED search returns HS2 notices from November 2016 only.

Advisers and the cost of control

Paying to find out what was bought

The government defence of the 2025–26 consultancy bill is that it was spent establishing what had been delivered for money already gone, rather than on further advice about the railway. That is a claim about purpose, and it is testable against the reset's own outputs: the baseline due in spring 2027, and the sums actually recovered as disallowable.

Reset, total expected — Jan 2025 – spring 2027£101m spent to Mar 2026
spent£101m
expected£153m
Consultancy, HS2 Ltd — two different basescalendar 2025 vs FY 2025–26
CY 2025£65m
FY 25–26£77.8m
Consultancy, calendar 2025 ~£65m

Reported spend with consultancies over the calendar year, during the first year of the reset.

Press reporting · 2026-05

Press-derived, not a departmental or audited figure. The Hansard answer of 22 June 2026 gives £77.8m on a 2025–26 financial year basis — use that one.

Back-office roles removed 300+

Cited as evidence of HS2 Ltd being reshaped into a simpler delivery company.

Hansard, Lords · 2026-06-22

Set against the NAO finding of too many staff in central functions, too few in front-line delivery, and gaps in commercial, contract management and systems integration capability. https://hansard.parliament.uk/Lords/2026-06-22/debates/005F6C33-3A0E-40B8-A77B-805C7043D65D/HS2LtdConsultants

Commercial function New CCO

A new chief commercial officer and additional commercial staff appointed through the reset, alongside a centralised cost-assurance function.

HS2 Ltd announcement · 2026-07-31

Civils renegotiation has run on a verified-cost basis since April 2025 — establishing what was actually delivered before agreeing new terms. https://mediacentre.hs2.org.uk/news/hs2-signs-new-civil-engineering-contract-deals

Future cost risk avoided (claimed) ~£2bn

Put to HS2 Ltd by the PAC on 14 September 2026. Mark Wild described it as avoiding future cost risk, not as a guaranteed saving from the contract resets.

Construction News · 2026-09-15

As reported from the hearing; check the HC 611 transcript before quoting. Neither a booked saving nor a departmental commitment. Earlier coverage of the NAO report had presented the same figure as a targeted saving. https://www.constructionnews.co.uk/civils/hs2/hs2-ltd-hopes-to-seal-contract-resets-with-scs-and-bbv-by-december-15-09-2026/

Live notice harvest

Queried from the platforms themselves

Contracts Finder and TED are searched directly; both need a POST request that a browser cannot make across origins. Find a Tender offers no buyer or keyword filter at all, so it is crawled date by date in the background and filtered on buyer name. Figures below are pre-harvested and stored, so the panel is never empty on arrival.

No stored harvest yet — press Refresh, or wait for the scheduled run.
Contracts FinderNot yet harvestedThe first harvest runs on the next scheduled tick, or press Refresh.
TEDNot yet harvestedThe first harvest runs on the next scheduled tick, or press Refresh.
Find a TenderNot yet harvestedThe first harvest runs on the next scheduled tick, or press Refresh.

Declared values are as recorded on each notice. Some are framework ceilings rather than contract values, one procurement can appear on more than one platform, and de-duplication is by notice ID rather than by underlying contract — so treat the combined total as an upper bound on what has been declared, not a precise figure.

Scrutiny trail

What has been examined, and what has not

The NAO reported mid-reset, deliberately, to give Parliament something to hold. The PAC took evidence on 14 September; its report, the last two civils resets and the next six-monthly report are the open items.

Data and sources

Take the numbers with you

Everything on this page is available as JSON or CSV, provenance grade included. gap.csv carries the year-by-year payments and declared-value series behind the chart above. Nothing here is a live feed — the dataset is versioned and dated, so a figure you quote can be traced to the version it came from.

  1. National Audit Office, High Speed Two reset, HC 52 2026-27, 2026-06-29. https://www.nao.org.uk/reports/high-speed-two-reset/
  2. Department for Transport, HS2 six-monthly report to Parliament, May 2026, 2026-05-19. https://www.gov.uk/government/speeches/hs2-6-monthly-report-to-parliament-may-2026
  3. Department for Transport, HS2 Phase 1: decision to continue delivery following programme reset — Accounting Officer assessment summary, 2026-05-19. https://www.gov.uk/government/publications/department-for-transports-accounting-officer-assessment-summaries-for-the-government-major-projects-portfolio
  4. House of Lords, HS2 Ltd: Consultants — oral answer, 2026-06-22. https://hansard.parliament.uk/Lords/2026-06-22/debates/005F6C33-3A0E-40B8-A77B-805C7043D65D/HS2LtdConsultants
  5. HS2 Ltd, HS2 signs new civil engineering deals, 2026-07-31. https://mediacentre.hs2.org.uk/news/hs2-signs-new-civil-engineering-contract-deals
  6. HS2 Ltd, HS2 Ltd annual report and accounts 2025 to 2026 (period ending 31 March 2026), 2026-07-10. https://www.gov.uk/government/publications/hs2-ltd-annual-report-and-accounts-2025-to-2026
  7. Committee of Public Accounts, Delivering HS2 and Euston — inquiry, 2026-05-18. https://committees.parliament.uk/work/9790/delivering-hs2-and-euston/
  8. HS2 Ltd / Alstom / Hitachi Rail, Hitachi-Alstom High Speed contract award, Phase 1 rolling stock and 12-year maintenance, 2021-12-09. https://mediacentre.hs2.org.uk/news/hs2-ltd-awards-landmark-rolling-stock-contracts-to-hitachi-alstom-joint-venture
  9. Construction News, HS2 inks contract reset with two civils JVs, 2026-07-31. https://www.constructionnews.co.uk/civils/hs2-inks-contract-reset-with-two-civils-jvs-31-07-2026/
  10. Financial Times, reported May 2026, Reporting of HS2 consultancy spend, calendar year 2025, 2026-05. No public URL — press reporting, cited for context only.
  11. Chris Smith MCIPS, compiled January 2026, Declared values of HS2 contract award notices on Contracts Finder, Find a Tender and OJEU TED, 2018–2025, set against cumulative supplier payments (payment series rebuilt October 2026), 2026-01. No public URL — press reporting, cited for context only.
  12. Department for Transport; compiled by Chris Smith MCIPS, October 2026, DfT: spending over £25,000 — monthly transparency data, January 2017 to July 2026 (HS2 Ltd entity rows), 2026-10-29. https://www.gov.uk/government/collections/dft-departmental-spending-over-25000
  13. Compiled by Chris Smith MCIPS, October 2026, HS2 Ltd contract award notices on Contracts Finder, Find a Tender and TED, 2015 to October 2026, 2026-10-30. No public URL — press reporting, cited for context only.
  14. Chris Smith MCIPS, Written evidence to the Committee of Public Accounts, HS2 and Euston: Recall (HS20003), 2023-11. https://committees.parliament.uk/writtenevidence/126367/pdf/
  15. Committee of Public Accounts, Oral evidence: Delivering HS2 and Euston, HC 611 — Shanmugalingam, Creamer, Wild, 2026-09-14. https://committees.parliament.uk/oralevidence/18078/pdf/
  16. Committee of Public Accounts, Delivering HS2 and Euston — oral evidence session, 14 September 2026, 2026-09-14. https://committees.parliament.uk/event/28101/formal-meeting-oral-evidence-session/
  17. Construction News, HS2 hopes to seal SCS and BBV contract resets by Christmas, 2026-09-15. https://www.constructionnews.co.uk/civils/hs2/hs2-ltd-hopes-to-seal-contract-resets-with-scs-and-bbv-by-december-15-09-2026/
  18. New Civil Engineer, HS2 awards £856M Birmingham depot contract as project reset continues, 2026-05-11. https://www.newcivilengineer.com/latest/hs2-awards-856m-birmingham-depot-contract-as-project-reset-continues-11-05-2026/
  19. GOV.UK, Euston Delivery Company — organisation page (executive non-departmental public body, sponsored by DfT), 2026-10. https://www.gov.uk/government/organisations/euston-delivery-company
  20. HS2 Ltd, Letter from HS2 Ltd to Chris Smith MCIPS, reference CEO-25-1496, 2026-03-06. No public URL — press reporting, cited for context only.
  21. HS2 Ltd, via WhatDoTheyKnow, Main Works Civils Contract values — request by Chris Smith, answered under the EIR 2004 with information withheld under regulations 12(5)(d) and 12(5)(e), 2026-10. https://www.whatdotheyknow.com/request/1505331
  22. Chris Smith MCIPS, Letter to Mark Wild, Chief Executive, HS2 Ltd, on the procurement transparency gap, 2025-07-06. No public URL — press reporting, cited for context only.