Published on Find a Tender but not on Contracts Finder
£1.97bnHS2 Rolling Stock Manufacture and Maintenance Services — Hitachi Rail Limited
FTS notice 2022/S 000-000805, published 11 January 2022. Value excluding VAT £1,970,000,000.
Two thirds of the money spent. One third of the work done.
Every figure below is taken from a published source and carries the reference. Cost figures are only comparable within a single price base, so the basis is a control, not a footnote.
Programme position
HS2 Ltd payments of £25k or more since January 2017, nominal prices, from DfT monthly spending data. Includes payments for the cancelled Phase 2.
Totalled from 115 DfT monthly files, January 2017 to July 2026, excluding a £590m VAT remittance to HMRC in July 2019. The NAO put total programme expenditure at £46.8bn to 31 March 2026 (HC 52), on a different basis. https://www.gov.uk/government/collections/dft-departmental-spending-over-25000
Expected total. £101m spent by 31 March 2026. The reset runs from January 2025 to spring 2027.
Nominal prices. The reset concludes with a fully assured cost and schedule baseline in spring 2027. https://www.nao.org.uk/reports/high-speed-two-reset/
HS2 Ltd spend on consultancy in the financial year, stated in answer to a Lords oral question.
Lord Hendy of Richmond Hill, HS2 Ltd: Consultants, House of Lords, 22 June 2026. https://hansard.parliament.uk/Lords/2026-06-22/debates/005F6C33-3A0E-40B8-A77B-805C7043D65D/HS2LtdConsultants
Identified by HS2 Ltd and the main works civils and stations contractors as outside contract scope or unsupported by records, as at May 2026.
Cost verification now runs quarterly. Where costs are disallowed, HS2 Ltd adjusts expenditure and seeks recovery from the joint ventures. https://www.nao.org.uk/reports/high-speed-two-reset/
Cost and schedule
The May 2026 estimate is a range, not a number. HS2 Ltd's chief executive has set an ambition inside the lower half of that range; the NAO view is that the estimate still carries high uncertainty until the baseline lands in spring 2027.
Two thirds from scope missed at the outset, underestimation and inefficient delivery. One third from inflation.
Cost estimates will now be refreshed for inflation every two years rather than held for seven. https://www.gov.uk/government/speeches/hs2-6-monthly-report-to-parliament-may-2026
Latest date the full railway could open is December 2043, against an earliest 2031 on the 2020 schedule.
Civil engineering across the line of route is at least four years behind; testing and commissioning was underestimated by roughly a further three. https://www.nao.org.uk/reports/high-speed-two-reset/
Now an executive non-departmental public body sponsored by DfT. Chief executive and chair still being appointed. A PPP for the HS2 station is being explored.
Took the directing role for the Euston campus in April 2026. DfT told the PAC on 14 September 2026 that chief executive interviews had been held. Early market engagement began October 2025; the first stage of preliminary market engagement followed in February 2026, testing appetite for a design, build, finance and maintain structure. Trade press reported at the end of October 2026 that the chief executive search was still running and the search for a chair had been paused. https://www.gov.uk/government/organisations/euston-delivery-company
Spent by March 2026, before any HS2 station there is contracted.
Stated in the Public Accounts Committee notice for its 14 September 2026 session, drawing on the NAO report. https://committees.parliament.uk/event/28101/formal-meeting-oral-evidence-session/
The transparency gap
Contracts commit money before it is spent, so the declared value of award notices should sit above cumulative payments. Until 2019 it did. Payments overtook declared value in 2020, and the distance has widened every year since.
| Notice type | Contracts Finder | Find a Tender | FTS as share of CF |
|---|---|---|---|
| Contract (tender) notices | 206 | 33 | 16% |
| Contract award notices, value over £115,658 | 247 | 37 | 15% |
Publication on Find a Tender is a treaty obligation under the WTO Government Procurement Agreement and the UK–EU Trade and Cooperation Agreement. The difference in notice format between the two platforms does not account for a gap of this size.
Written evidence to the Committee of Public Accounts, HS2 and Euston: Recall (HS20003). committees.parliament.uk/writtenevidence/126367/pdf/PAC written evidence · 2023-11
HS2 Ltd wrote on 6 March 2026 (CEO-25-1496) that the gap between published award values and published spend is not disputed, and that the four Main Works Civils Contracts costing more than their estimates at award "will form a major part of the gap". The request asked for the figures behind that explanation.
7 of 8 items withheld. Received 23 September 2026; answered October 2026, late. Handled under the Environmental Information Regulations 2004, not FOIA. Public interest held to favour withholding "at this time" because the contracts are being renegotiated, and to protect confidential Board reporting. The EKFB and Align deeds of variation had been signed on 31 July 2026, before the request was made.
| # | Asked for | Outcome | Exception |
|---|---|---|---|
| 1 | Total of the Prices for each contract at the start of Stage 2, April 2020 | Withheld | EIR 12(5)(d), 12(5)(e) |
| 2 | Total of the Prices now, with all implemented compensation events | Withheld | EIR 12(5)(d), 12(5)(e) |
| 3 | Value of compensation events implemented since Notice to Proceed | Withheld | EIR 12(5)(d), 12(5)(e) |
| 4 | Latest Anticipated Final Cost reported to the Board or ARAC | Withheld | EIR 12(5)(d), 12(5)(e) |
| 5 | Cumulative Price for Work Done to Date certified | Withheld | EIR 12(5)(d), 12(5)(e) |
| 6 | Value of the new EKFB and Align agreements, and of each contract just before signature | Withheld | EIR 12(5)(d), 12(5)(e) |
| 7 | Latest consolidated schedule of contract values given to the BoardNo consolidated schedule; values were reported to the Board by project, last in June 2024. | Withheld | EIR 12(5)(d), 12(5)(e) |
| 8 | Whether an award, UCR reg 88(5) modification or PA23 change notice was published for the EKFB and Align agreements, and the ground relied onThe agreements were deeds of variation to UCR 2016 contracts, considered under reg 88, so no PA23 notice and no award notice was required. The response does not say whether a reg 88(5) modification notice was published, or which permitted ground was relied on. | Partly answered |
Response, Annex A (item-by-item answers) and Annex B (public interest tests). whatdotheyknow.com. Premise from HS2 Ltd letter CEO-25-1496, 6 March 2026.
HS2 Rolling Stock Manufacture and Maintenance Services — Hitachi Rail Limited
FTS notice 2022/S 000-000805, published 11 January 2022. Value excluding VAT £1,970,000,000.
Resilience and Assurance Framework Agreement for Interchange Station — Skanska Construction UK Limited
Published 28 September 2022 on Contracts Finder with a total contract value of £0.
BBV HS2 MWCC North, Delta Junction — PSV erection tools certification technical assistance
Published 30 November 2022. Supplier recorded as the notice publisher rather than the contractor.
Main works civils, Stage 1 award
OJEU TED notice 344354-2017 declared the value as "Variable". No Stage 2 construction award notice appears on any platform.
Main works civils, EKFB and Align, deeds of variation signed 31 July 2026
HS2 Ltd says no award notice or Procurement Act change notice was required, as these were modifications to UCR 2016 contracts. Old and new values were withheld under EIR 12(5)(d) and 12(5)(e) in response to FOI-26-6379.
Notice series compiled by Chris Smith MCIPS from Contracts Finder, Find a Tender and OJEU TED, January 2026. Payment series rebuilt October 2026 from all 115 DfT monthly spending files, January 2017 to July 2026 (HS2 Ltd entity rows). Blue marker: independent compilation rather than a departmental publication. HS2 Ltd does not dispute that the gap exists; what it signifies is contested.
Contracts and suppliers
The 2020 commercial model put nearly all risk on the taxpayer and did not reward hitting cost or schedule targets. The £15bn allocated in 2020 for the Phase 1 main civils was exhausted by 2024 with the works far from finished. Renegotiation has run on a verified-cost basis since April 2025 and is not yet complete.
| Package | Held by | Scope | Value | Reset status |
|---|---|---|---|---|
| Main works civils — north Chilterns to Warwickshire | EKFBEiffage, Kier, Ferrovial Construction, BAM Nuttall | 80km | Withheld | Deed of variation signed 31 Jul 2026 |
| Main works civils — outer London and south Bucks | AlignBouygues Travaux Publics, Sir Robert McAlpine, VolkerFitzpatrick | 24km incl. Chiltern Tunnel, Colne Valley Viaduct | Withheld | Deed of variation signed 31 Jul 2026 |
| Main works civils — West Midlands | Balfour Beatty VINCI | 90km | Withheld | In negotiation · target: Christmas 2026 |
| London tunnels | Skanska Costain STRABAG | 21km, West Ruislip to Euston | Withheld | In negotiation · target: Christmas 2026 |
| Old Oak Common station | Balfour Beatty VINCI SYSTRA | 14-platform interchange | ~£1bn | Award value, pre-reset |
| Birmingham Curzon Street station | Mace Dragados | 7-platform terminus | ~£570m | Award value, pre-reset |
| Interchange station, Solihull | Laing O'Rourke | 4-platform station | ~£370m | Award value, pre-reset |
| Euston HS2 station | Euston Delivery Company (client) | Design stage; PPP under exploration | — | Not contracted |
| Rolling stock and 12-year maintenance | Hitachi-Alstom High Speed (HAH-S) | 54 trains — Newton Aycliffe, Derby, Crewe | £1.97bn | Award value, Dec 2021 |
| Washwood Heath rolling stock depot and Network Integrated Control Centre | TWA JVTaylor Woodrow Infrastructure, Aureos Rail | 70ha site, Birmingham | ~£856m | Awarded May 2026, during the reset |
Station and rolling stock values are as awarded and pre-date the reset; they are not restated on the May 2026 basis. HS2 Ltd told the PAC in September 2026 it expects to realign two station contracts and the rolling stock contract to the reset programme by March 2027. The Washwood Heath depot value is as reported at award. Station programme cost estimates — which cover far more than the construction contract — are shown separately above.
Every published award
Every contract award, modification and voluntary transparency notice published with HS2 Ltd as the buyer — on Contracts Finder since 2015, Find a Tender since 2021, and the EU's TED. One row per awarded lot. The same award published on more than one platform is counted once. Values are as declared in the notice: a contract's value when awarded, not what has been paid.
| Published | Contract | Supplier | Declared value | Notice |
|---|---|---|---|---|
| Loading… | ||||
Contracts Finder searched month by month for “HS2”, “High Speed Two” and “High Speed 2”, kept where the publishing organisation is HS2 Ltd. Find a Tender: every release since January 2021 (326,595), kept where HS2 Ltd is a buyer by Companies House number or name. TED: notices with HS2 Ltd as buyer, with suppliers and lot values read from the notice XML. Notices published by HS2's own contractors (EKFB, BBV, SCS, Align and others) are not HS2 Ltd contracts and are excluded. Duplicates are matched automatically by supplier and value, by identical value over £1m within 400 days, or by a Contracts Finder value equal to a whole multi-lot notice. TED search returns HS2 notices from November 2016 only.
Advisers and the cost of control
The government defence of the 2025–26 consultancy bill is that it was spent establishing what had been delivered for money already gone, rather than on further advice about the railway. That is a claim about purpose, and it is testable against the reset's own outputs: the baseline due in spring 2027, and the sums actually recovered as disallowable.
Reported spend with consultancies over the calendar year, during the first year of the reset.
Press-derived, not a departmental or audited figure. The Hansard answer of 22 June 2026 gives £77.8m on a 2025–26 financial year basis — use that one.
Cited as evidence of HS2 Ltd being reshaped into a simpler delivery company.
Set against the NAO finding of too many staff in central functions, too few in front-line delivery, and gaps in commercial, contract management and systems integration capability. https://hansard.parliament.uk/Lords/2026-06-22/debates/005F6C33-3A0E-40B8-A77B-805C7043D65D/HS2LtdConsultants
A new chief commercial officer and additional commercial staff appointed through the reset, alongside a centralised cost-assurance function.
Civils renegotiation has run on a verified-cost basis since April 2025 — establishing what was actually delivered before agreeing new terms. https://mediacentre.hs2.org.uk/news/hs2-signs-new-civil-engineering-contract-deals
Put to HS2 Ltd by the PAC on 14 September 2026. Mark Wild described it as avoiding future cost risk, not as a guaranteed saving from the contract resets.
As reported from the hearing; check the HC 611 transcript before quoting. Neither a booked saving nor a departmental commitment. Earlier coverage of the NAO report had presented the same figure as a targeted saving. https://www.constructionnews.co.uk/civils/hs2/hs2-ltd-hopes-to-seal-contract-resets-with-scs-and-bbv-by-december-15-09-2026/
Live notice harvest
Contracts Finder and TED are searched directly; both need a POST request that a browser cannot make across origins. Find a Tender offers no buyer or keyword filter at all, so it is crawled date by date in the background and filtered on buyer name. Figures below are pre-harvested and stored, so the panel is never empty on arrival.
Declared values are as recorded on each notice. Some are framework ceilings rather than contract values, one procurement can appear on more than one platform, and de-duplication is by notice ID rather than by underlying contract — so treat the combined total as an upper bound on what has been declared, not a precise figure.
Scrutiny trail
The NAO reported mid-reset, deliberately, to give Parliament something to hold. The PAC took evidence on 14 September; its report, the last two civils resets and the next six-monthly report are the open items.
Data and sources
Everything on this page is available as JSON or CSV, provenance grade included. gap.csv carries the year-by-year payments and declared-value series behind the chart above. Nothing here is a live feed — the dataset is versioned and dated, so a figure you quote can be traced to the version it came from.